An item or requirement that will prevent an activity from starting, advancing or completing as planned. Typical constraints on design tasks are inputs from others, clarity of requirements criteria for what is to be produced or provided, approvals or releases, and labor or equipment resources. Typical constraints on construction tasks are the completion of design or prerequisite work; availability of materials, information and directives. Screening tasks for readiness is assessing the status of their constraints. Removing constraints is making a task ready to be assigned.
A list of Constraints with identification of an individual promising to resolve the item by an agreed date. Typically developed during a review of the Six Week Look-Ahead Plan when it is discovered that activities are not constraint free.
A Quality Task must be “Defined” — it must have a beginning and end – it should be clear to all when it has been completed.
Where two or more tasks are sufficiently related that one cannot be started (or finished) without a certain measure of progress or completion having been achieved by the other. Waiting on release of work. E
The act of releasing an item or activity to the person or group performing the next step or operation on that item or activity. Example: a structural steel design is “handed off” to the steel detailer to complete shop drawings; a room (or portion) that has been framed is “handed off” to the drywall installer; or all construction on a floor of a hospital is completed and it is “handed off” to the hospital personnel to begin staff-and-stock activities.
The Conditions of Satisfaction discussed and explicitly agreed upon between the parties to a hand-off. I
The extent to which a plan is an accurate forecast of future events, measured by Percent Plan Complete (PPC).
Work that must be performed by others in order for you to perform your work.
Determining the status of tasks in the look-ahead window relative to their constraints, and choosing to advance or retard tasks based on their constraint status and the probability of removing constraints.
A “sequenced” assignment should release work to another Performer and in no case should it hinder another assignment or cause other crews to do additional work. Quality criterion for selecting assignments among those that are sound in priority order and in constructability order.
Preventing the release work to production units because it does not meet quality criteria; the work is not a quality assignment. It is akin to “stopping the assembly line,” rather than advancing a defective product. The purpose of shielding is to reduce uncertainty and variation, thereby providing production units with greater opportunity to be reliable.
Quality criterion for assignments whereby the amount of work included in an assignment is made to match the capacity of the production unit that will do the work. The Performer should have a very reasonable expectation that the assignment can be completed by the number of people available to do the job.
Quality criterion for assignments that tests whether or not assignments have had all constraints removed. The Performer of an assignment should know that the materials, tools, staff and information to complete an assignment are available before accepting it.
Making assignments to a production unit, or a resource within a production unit, that absorbs less than 100% of its capacity. Under-loading is necessary to accommodate variation in processing time or production rate, in order to assure plan reliability. Under-loading is also done to release time for workers to take part in training or learning, conducting first-run studies, implementing process improvements, or for equipment to be maintained.